Another successful air conditioning installation was part of a complete refurbishment of three duplex apartments in the Borough of Kensington and Chelsea by Cool You. As part of a complete building refurbishment, this air conditioning installation marks a significant achievement for our team.
61 Harrington Gardens is within the Courtfield Conservation Area. However, this project presented unique challenges due to its historical significance and the strict planning laws that prohibited standard air conditioning systems with external condenser boxes.
Cool You was the clear choice for this project. Based on our proven expertise in providing air conditioning solutions for listed buildings and apartments within conservation areas, the client decided. Cool You’s track record of successful installations in similar environments instilled confidence in our client and their team.
Our highly skilled engineering team devised a tailor-made solution.
Our highly skilled engineering team successfully delivered a robust, customised solution through effective collaboration with the client’s architects and contractors. This comprehensive plan featured a well-coordinated combination of air-cooled mono, multi-split internal condensers vented outside. There was also a conventional external condenser and an efficient heat recovery system. By integrating these components with innovative ducted (hidden) room units that utilise advanced DC inverter technology, we achieved a seamless, fully concealed installation within the building’s structure.
Our design and installation team carefully planned the position of the internal condensing units. Placing these units in the lower ground vault and loft spaces allowed us to ensure a streamlined installation process. The ducted fan coil units were also positioned within ceiling voids, showcasing our strong attention to detail and reinforcing our commitment to delivering high-quality results.
During phase one, we effectively routed all refrigerant pipework to be enclosed by the contractors. Our team, recognised for its adaptability, harmonised the installation with the contractor’s schedule, ensuring a smooth and efficient workflow. In the subsequent phase, we successfully installed ducting from the air-cooled internal condensers to the external wall, connecting them through pre-drilled holes that complied with the main contractor’s specifications.
It’s worth noting that this air conditioning installation project progressed without requiring planning permission, further enhancing its efficiency.
Air conditioning installation as part of an apartment refurbishment – For this project, we installed:
Apartment One
2 x 5.3kw Air Cooled Mono-Split Internal Condensers for master bedroom and second bedroom serving 2 x 5.3kw Ducted Units
1 x 5.3kw Air Cooled Dual-split Internal
Condenser for third bedroom and multi-media room serving 2 x 2.6kw Ducted Units
1 x Ventaxia Heat Recovery System for media room
Apartment Two
1 x 7kw Air Cooled Dual-Split Internal Condenser for master bedroom and second bedroom serving 1 x 5.3kw and 2.6kw Ducted Units
Apartment Three
1 x Mitsubishi 14kw mini VRF Condenser serving (located on the apartments outside terrace)
1x 7kw ducted room unit, 1 x 3.6kw Ducted Room Unit and 2 x 2.8kw Ducted Room Units